Experiment 4. POPLU
POPLU deposition tunnel end plug experiment will be implemented in ONKALO demonstration area at the planned disposal depth within POPLU project jointly by Posiva and SKB.
-
Planning and design 2012-2013.
-
Construction and implementation 2013-2014.
-
Testing activities 2014-2015.
-
Reinforced low pH concrete is the main component in the wedge plug. The plug structure is a composite plug and a modified backfill section is needed behind the plug for experimental purposes. Length of the plug is 6 meters and the diameter is 5,5 meter.
-
POPLU and DOMPLU will be evaluated together.